NEW QUESTION # 43
Determine the correct formula and date for the late finish for Activity 2002.
- A. LS.2003 - 1 day -> 10-06-01.
- B. LS.2003 - 1 day -> 10-05-01.
- C. LS.2003 - 1 day -> 11.06.01.
- D. LS.2003 + 1 day -> 10-07-01.
Answer: B
NEW QUESTION # 44
Which of the following is the type of comparative negligence statute?
- A. 51 percent rule
- B. 50/50 rule
- C. All of the above
- D. Pure approach
Answer: C
NEW QUESTION # 45
Constraints control events or activities that __________________.
- A. May be over-ridden by activity logic.
- B. Affect only the backward pass.
- C. Affect only the forward pass.
- D. Are not based on project relationships.
Answer: A
NEW QUESTION # 46
When using a detailed estimate as the basis for work package/activity durations, which element does NOT need to be identified before the activity durations can be calculated?
- A. Projected crew size
- B. Hours in a standard work day
- C. Estimated labor hours
- D. Estimated cost
Answer: A
NEW QUESTION # 47
Which of the following is NOT the advantage of proprietary officers?
- A. Impartiality
- B. Quality of personnel
- C. Loyalty
- D. Prestige
Answer: A
NEW QUESTION # 48
Is activity 7001 pictured correctly in the precedence diagram?
- A. Yes, except the early finish date is not shown.
- B. Yes, the duration is 48 days.
- C. No, the start-to-start and finish-to-finish relationships are backwards.
- D. No, the total float is not shown correctly.
Answer: B
Explanation:
Activity Details (7001 - "Permanent Roads"):
* Duration: 48 days in the Normal schedule.
* Precedence Diagram Information: The schedule correctly reflects the logic and relationships as FS (Finish-to-Start) with successors.
Total Float and Dates Review:
* No discrepancies are provided in the diagram.
* Early Start (ES) and Early Finish (EF) align with the planned duration and dependencies.
Validation:
* Total float is not specified as incorrect.
* Early Finish dates, while not explicitly displayed, do not contradict the sequence.
* Start-to-Start and Finish-to-Finish relationships are correctly oriented.
Conclusion:The activity is correctly represented with a duration of 48 days.
NEW QUESTION # 49
What considers all aspects of the security operation on a continuing basis?
- A. Security Vulnerability
- B. Operational Audit
- C. Inspection criterion
- D. Data-security Act
Answer: B
NEW QUESTION # 50
The linear scheduling velocity diagram has the following two-axis:
- A. Location and crew size
- B. Time and location
- C. Time and crew size
- D. Time and rate of progress
Answer: D
NEW QUESTION # 51
Why does activity 1001 have two successor activities?
- A. Because the late finish of 1001 and the late start of 7001 require two successors
- B. Because the problem could not effectively work with only one successor
- C. Because the duration of activities 2001, 2002 and 200.f require two successors
- D. Because there are two defined logic paths for the work
Answer: D
NEW QUESTION # 52
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
- A. B.
- B. C.
- C. S.
- D. W.
Answer: C
NEW QUESTION # 53
Some people are willing to copy software and resell it or give it away; this authorized copying of copyrighted computer programs is called:
- A. Identify theft
- B. Unauthorized access to software
- C. Software privacy
- D. War driving
Answer: C
NEW QUESTION # 54
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
- A. 09-15-01.
- B. 09-18-01.
- C. 09-28-01.
- D. 09-08-01.
Answer: D
NEW QUESTION # 55
Which of the following is NOT of the basic trends of security services?
- A. All of the above
- B. Disarm security personnel
- C. Regulate training and standards
- D. Attract better qualified individuals
Answer: A
NEW QUESTION # 56
Trimming off small amounts of money from many sources and diverting these slices into one's own or an accomplice's account is known as:
- A. Manipulation technique
- B. Auction planning
- C. Hostile applets
- D. Salami Technique
Answer: D
NEW QUESTION # 57
Crane operators require 1 hour prep and 1 hour clean-up and inspection per day. There is only 1 crane operator allocated per crane. Crane operators are not allowed to work more than 8 hours a day. Lunchtime break lasts 1 hour. Assuming a 10 minute cycle time, how many lifts per day can be expected?
- A. 36 lifts
- B. 48 lifts
- C. 24 lifts
- D. 30 lifts
Answer: A
NEW QUESTION # 58
The relationship between the two groups continues to be strained because of which key issue?
- A. All of the above
- B. Moonlight policies for public police
- C. Perceived competition
- D. Provision of services in borderline of responsibility
Answer: A
NEW QUESTION # 59
Background
Your name is Evan Marshal. You are the corporate scheduler for Happy Insurance Corporation (HIC), a general health insurance company located in Ridgemond, Illinois. HIC is very busy with 49 unique software development projects. The organization structure at HIC gives the project scheduling responsibility to the Project Manager assigned to each project. You are charged with coordination of the project schedules into a Master Schedule and quality control for scheduling on the individual development projects. You report directly to the Director of Information Services (DIS), Desmond Rayburn.
It has come to your attention Project JP-114 has fallen behind schedule and Rita Belateau, the Project Manager, wants to accelerate the project in order to reclaim lost time. Rita is a strong supporter of Total Quality Management and strives for zero failures; therefore she is assessing the need for overtime for resources assigned to an activity that is not projecting a completion prior to the early finish depicted in the current schedule.
You and Rita review the current schedule to identify which activities are on the critical path and which activities have plenty of float. The review reveals several activities have suffered less than planned productivity and have contributed to falling behind. In the process of this review, you and Rita also review the budget for Project JP-114 and notice not only the schedule has fallen behind but the cost to date is more than she had expected. To total budget is $150,000, planned to date is $30,000; expended to date is $37,000.
With nine months remaining until baseline contract completion, Rita needs to bring Project JP-114 back on track; knowing overtime for an extended period of time is not always the right answer, especially with the cost to date already over planned.
In order to truly understand the options available to help remedy the current situation, you and Rita brainstorm on several potential courses of action. All the potential courses of action will require an evaluation of budget impact versus schedule correction.
1. Pull the project team together and ensure everyone understands which activities are on the critical path.
Rita would like to use the existing project team and focus them on these critical path activities, laying out a plan for periodic overtime when needed to crunch through a deliverable. This approach could add approximately 20% to the budget.
2. Outsource various modules of activities to qualified and known consultants. This could drive up the costs and must be evaluated before implemented. Having an outside source working in parallel with the project team could also accelerate the schedule to mitigate some of the delays, as well as keep overtime down to a minimum for the project team. Potentially this could add as much as 40% to the budget, but could also be very productive schedule wise.
3. Mandatory overtime for the project team - entire project goes on a 50-hour work week. If the entire project team works overtime for an extended period of time, the budget could see an additional 60% increase.
4. The project continues as is completes the project late and accepts the penalties imposed. Penalties imposed for late delivery could add as much as 50% to the budget.
Assignment
Draft a proper memorandum to Desmond Raybum, IS Director, explaining in your own words:
a. the current problem and potential impact(s);
b. each course of action, stating advantages and disadvantages as appropriate; c. your recommendations, properly supported.
Please be sure to include the rationale for your recommendations. Be sure to summarize your thoughts and address (To, From, Date, and Subject/Project Name) and close the memo appropriately. If you are uncomfortable with the courses of action noted, provide your own with appropriate substantiation for your position. Limit your answer to one, full typewritten page (roughly three handwritten pages).
While your email can be a detailed as you like, be sure to write sufficiently to address each element of the assignment, yet not so long that you go beyond the scope of the exercise.Take time to read the problem and consider what you want Evan to say. Good luck!
Answer:
Explanation:
See the Explanation for complete Solution for this.
Explanation:
To: Desmond Rayburn, Director of Information ServicesFrom: Evan Marshal, Corporate SchedulerDate:
[Insert Current Date]Subject: Mitigation Plan for Project JP-114 Delays Current Problem and Potential ImpactsProject JP-114 has experienced schedule delays and cost overruns.
The project has expended $37,000 against a planned budget of $30,000 to date, exceeding the planned budget by 23%. Additionally, productivity issues have impacted critical path activities, further delaying progress.
With nine months remaining, failing to address these issues could result in penalties, further cost increases, and client dissatisfaction.
* Focus Existing Team on Critical Path with Periodic Overtime
* Advantages: Uses team familiarity; incurs a moderate budget increase (20%).
* Disadvantages: Risks resource strain and potential burnout if overtime is prolonged.
* Outsource Work to Consultants
* Advantages: Accelerates schedule by parallel work streams; minimizes internal team overtime.
* Disadvantages: Higher budget impact (up to 40%); requires effective integration of external deliverables.
* Mandatory Overtime (50-Hour Work Week)
* Advantages: Ensures rapid progress across the project.
* Disadvantages: Extremely high cost (60% increase); risks significant employee fatigue and declining morale.
* Continue as Is and Accept Late Delivery Penalties
* Advantages: No immediate resource strain.
* Disadvantages: Significant penalties (50% budget increase); damages stakeholder confidence and corporate reputation.
Courses of Action
RecommendationI recommend Option 1, combined with selective outsourcing (Option 2), to achieve the best balance of cost control and schedule recovery.
* Focus the internal team on critical path activities with targeted use of periodic overtime. This ensures efficient allocation of resources and minimizes strain while addressing the most urgent delays.
* Outsource select non-critical tasks to experienced consultants. This parallel effort reduces the workload on the internal team, limits overtime, and accelerates overall progress.
Rationale:This hybrid approach keeps the budget increase to approximately 30-35% while effectively addressing schedule delays. It balances cost efficiency, resource management, and stakeholder satisfaction.
Proper coordination will ensure smooth integration between internal and external teams.
ConclusionThis plan provides the most feasible path to bringing Project JP-114 back on track. It mitigates risks of extended delays while maintaining budget discipline. I am available for further discussions to outline a detailed implementation plan.
Best Regards,Evan MarshalCorporate Scheduler
NEW QUESTION # 60
What signal the entry of persons into a facility or an area while the system is in operation?
- A. Protection alarms
- B. Access door
- C. Invasions
- D. Intrusion alarms
Answer: D
NEW QUESTION # 61
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
- A. 09-15-01.
- B. 09-18-01.
- C. 09-28-01.
- D. 09-08-01.
Answer: D
Explanation:
Activity Duration in Crashed Schedule:
* For Activity 2002, the crashed duration is 28 days (refer to the table).
Start Date:
* The start date is August 12, 2001.
Adding the Duration:
* Starting from August 12, add 28 days. Ensure to account for weekends or holidays if the calendar used excludes them.
Finish Date Calculation:
* Starting on August 12 and counting 28 days gives the finish date as September 8, 2001.
NEW QUESTION # 62
The computers those are capable of great processing speed and data storage, allowing multiple users to utilize the system simultaneously is called:
- A. Workstations
- B. Mainframes
- C. Main computers
- D. Supercomputers
Answer: B